Ridge Pike Section D: Traffic Restrictions

Montgomery County’s Ridge Pike Improvement Project is a complex and lengthy roadway, drainage, sidewalk, and lighting construction project. This web  page will list current construction updates that will affect traffic flows along the corridor, and will be frequently updated as the County’s construction contractors complete various activities.

September 6, 2022

Barren Hill Road will have intermittent single lane closures on Tuesday, September 6, 2022. Single lane closures with flagging will be in effect from 9 a.m. to 3 p.m. on Barren Hill Road between Ridge Pike and Harts Lane for soil testing. The public is urged to use caution while traveling in construction zones.

August 22 – August 26, 2022

Pre-construction activities will continue on Ridge Pike between Crescent Avenue and Northwestern Avenue during the week of Monday, August 22, 2022. Single lane closures with flagging will be in effect from 9 a.m. to 3 p.m. from August 22-26 in various locations throughout the corridor for tree clearing and utility relocation. The public is urged to use caution while traveling in construction zones.

August 15 – August 19, 2022

Pre-construction activities will continue on Ridge Pike between Crescent Avenue and Northwestern Avenue during the week of Monday, August 15, 2022. Single lane closures with flagging will be in effect from 9 a.m. to 3 p.m. from August 15-19 in various locations throughout the corridor for tree clearing and utility relocation. The public is urged to use caution while traveling in construction zones.

August 8 – August 17, 2022

Rolling lane closures will occur along Ridge Pike from Crescent Avenue to Philadelphia in preparation for construction work. A temporary signal has been installed at the intersection of Manor Road and Ridge Pike and will go live on 8/10/2022.  Residents and commuters may notice a slight difference in the timing of the new signal.  The next intersection to receive a temporary signal will be Church Road/Harts Lane and Ridge Pike.

August 1 – August 7, 2022

Pre-construction activities will continue on Ridge Pike between Crescent Avenue and Northwestern Avenue during the week of Monday, August 1, 2022. Single lane closures with flagging will be in effect from 9 a.m. to 3 p.m. from August 1-5 in various locations throughout the corridor for tree clearing and utility relocation. The public is urged to use caution while traveling in construction zones.

July 25 – July 30, 2022

Pre-construction activities will continue on Ridge Pike between Crescent Avenue and Northwestern Avenue the week of Monday, July 25, 2022.  Single lane closures with flagging will be in effect from 9 AM to 3 PM during the week of the 25th in various locations throughout the corridor for tree clearing and utility relocation.  Please use caution while traveling in construction zones.

July 18 – July 22, 2022

Pre-construction activities will begin on Ridge Pike between Crescent Avenue and Northwestern Avenue on Monday, July 18, 2022. Single lane closures with flagging will be in effect from 9 AM to 3 PM during the week of the 18th in various locations throughout the corridor for tree clearing. Please use caution while traveling in construction zones.